Steps For Meeting Ordinance Requirements 
Steps For Meeting Ordinance Requirements

Step 1:
The Ordinance requirements apply to projects within the unincorporated areas of the County of Los Angeles. After you have contacted Building & Safety to begin the permit process, please obtain a Recycling and Reuse Plan from the Forms and Resources page. If further advisement is needed, please contact the Construction & Demolition Unit at (626) 458-3551.

Step 2:
Submit the Recycling and Reuse Plan. Forms may be submitted via fax at (626) 737-1723, via the U. S. Postal Service or a parcel service, or at the public counter of the Environmental Programs Division. The public counter is open from Monday through Thursday from 7 a.m. to 5 p.m., and is located at 900 South Fremont Avenue, Annex Building 3rd Floor, Alhambra. Once the Recycling and Reuse Plan is approved, please file a copy with Building & Safety so you may receive clearance on the required permit(s).

Step 3:
If anything changes, submit an Amendment to the Construction & Demolition Unit. The most common reason for an Amendment is to request additional time to complete a project. If the project requires a change of facilities, the Construction & Demolition Unit must first approve the facilities to be used. The use of a facility which has not been approved may lead to a violation.

Step 4:
If required, submit a 90 Day Report to the Construction & Demolition Unit no later than 90 days after issuance of the first permit for the project.

Step 5:
If required, submit an Annual Progress Report to the Construction & Demolition Unit on or before March 1 of every year, until project completion. An Annual Progress Report is not required if the County has been notified that a Final Compliance Report will be submitted on or before May 30 of the same year.

Step 6:
Submit a Final Compliance Report to the Construction & Demolition Unit within 45 days of project completion. Failure to file a Final compliance Report upon the completion of a project will lead to a violation.


  Sponsored by the County of Los Angeles
Department of Public Works
Environmental Programs Division
900 S. Fremont Ave, 3rd Floor Annex
Alhambra, CA 91803-1331
Call toll free at 1(888)CLEAN LA

DPW Logo  
 
DPW Home | lacounty.gov | Site FAQ | Privacy & Security Policy | Accessibility | Terms of Use | Feedback | Contact Us